9 ya 12 marla ghar ka budget plot label se final nahi hota. Contractor jis covered area aur scope ko price karta hai usay pehle likhna zaroori hai. Neeche do illustrative project budgets hain. In ke per-sqft inputs market quotations ya current city rates ka claim nahi.

Pehle area schedule banayein
| Scenario | Ground floor | First floor | Total covered area |
|---|---|---|---|
| 9 marla example | 1,600 sq ft | 1,400 sq ft | 3,000 sq ft |
| 12 marla example | 2,100 sq ft | 1,900 sq ft | 4,000 sq ft |
Ye floor areas approved coverage ratios nahi. Plot dimensions, local bylaws, setbacks aur drawings se apni actual quantities lein. Double storey ka covered area hamesha plot area × 2 nahi hota.
Quoted rate ko project total mein badlein
| Illustrative input | 3,000 sq ft | 4,000 sq ft |
|---|---|---|
| Grey scope: Rs 3,000/sq ft | Rs 9,000,000 | Rs 12,000,000 |
| Complete scope: Rs 6,500/sq ft | Rs 19,500,000 | Rs 26,000,000 |
Agar complete rate grey work ko already cover karta hai to dono totals jama na karein. Complete 19.5 million ke upar grey 9 million dobara jorna double counting hogi. Contractor se written inclusion list ke baghair complete lafz par bharosa na karein.
Quote A sasti nazar aaye lekin scope missing ho
9 marla example mein A ka base total 19,500,000 hai, lekin gate/wall 500,000 aur utility connections 200,000 excluded hain. Comparable total 20,200,000 hua. B same scope 20,000,000 mein deta ho to B ka normalized total 200,000 kam hai. Material specification, workmanship aur schedule ab bhi independently compare karne hain.
Price change ka sensitivity check
3,000 sq ft par rate mein har Rs 100 ka farq budget ko Rs 300,000 se badalta hai. 4,000 sq ft par wahi farq Rs 400,000 hai. Unpriced finishing allowance ko zero na likhein. Unknown line ko quotation ki missing information samjhein aur written amount le kar comparison dobara karein.
Cash flow aur contract se pehle
Total budget aur payment schedule alag banayein. Mobilization, structure milestones, finishing procurement aur final inspection ki payments contract ke mutabiq likhein. Scope change ka written process rakhein. Contingency ka example 20 million × 10% = 2 million hai, lekin ye project-specific risk allowance hai, statutory charge ya recommended universal percentage nahi.
Construction Quote Comparison Kit mein 2–3 quotations, exclusions aur allowances daal kar same-scope totals aur CSV nikalein. Preliminary area estimate ke liye House Construction Cost Calculator use karein. Structural design, soil conditions aur actual bill of quantities ke liye relevant qualified professional ki assessment chahiye.
Calculator mein total covered area ka correct input
Is reference ke 3000/4000sqft examples total floor areas hain. Inhein manual covered-area field mein enter karne ke baad floors se dobara multiply na karein. Default plot footprints illustrative hain, approved coverage ya city building permission nahi.